Scope Statement

 

The 2006-2007 Resurrection Lutheran Church Capital Improvement Project consists of the following activities.  Project includes all items detailed in the work breakdown structure and the detailed decision table included later in this plan.

 

1.      Construction of a two story addition with classrooms, basement, and fellowship hall.

 

a.      Completion of architect drawings

b.      Obtaining of Permits

c.       Completion of site preparation including the installation of erosion, sediment and storm water management requirements

d.      Excavation of basement

e.       Installation of concrete foundation, walls and flooring, including exterior drain around footings.

f.        Installation of plumbing, electrical and HVAC for new structure, including hookup to existing well and septic system, and provisions to hook up to county sewer and water system.

g.      Construction of building, including installation of elevator between basement and second floor.

h.      Work is to be done according to plans, specifications, permit requirements, and industry standards.

 

2.      Construction of an expanded narthex tying existing church with new structure.

 

a.      Including provisions in the ceiling to house the HCAC equipment for the new building and plus housing future HVAC equipment to replace the existing systems supplying existing church structure.  It does not include any materials, equipment or labor for these future potential new HVAC systems, only for the HVAC necessary for the new building addition.

b.      Installation of new primary entranceway into church as well as a doorway from existing fellowship hall into expanded narthex.

c.       Removal of walls between existing narthex and new expanded narthex.  Does not include any materials, equipment or labor to make any changes to wall between existing narthex and worship area.

d.      Work to be done according to plans, specifications, permit requirements and industry standards.

 

3.      Shaping and paving of driveway.

 

a.      Includes both primary and overflow parking area (currently occupied by temporary trailers).

b.      Work to be done according to plans, specifications, permit requirements and industry standards.

 

4.      Renovation of existing fellowship hall.

 

a.      Includes construction of two offices for use by pastors.

b.      Includes installation of a conference area.

c.       Includes entranceway into new narthex area.

d.      Includes conversion of the northwest corner of the existing space to receive the kitchen expansion.

e.       Work to be done according to plans, specifications, permit requirements and industry standards.

 

5.      Remodeling of the warming kitchen

 

a.      Expansion of the current kitchen space into the current fellowship hall space, effectively doubling the length of the kitchen.

b.      Includes installation of following equipment as shown in the work breakdown structure: 1 dishwasher, 2 refrigerators, 2 electric ranges.

c.       Does not include provisions to make this a full functioning kitchen for use food preparation, this is a warming kitchen only.